Peters Construction will be the primary contractor to perform the full reconstruct of Riverside Drive from Velp Avenue to West Deerfield Avenue beginning April 1, 2021. 

The project includes:

  • removing existing asphalt
  • digging out the subgrade
  • installing new stone road base and repaving
  • adding curb and gutter
  • 6’ sidewalk on the south side
  • Full roadway lighting
  • Painted crosswalk
  • Pavement markings

A Village engineer will be onsite most of the project while work is being performed. Click here for a letter sent to area businesses, construction schedule, and site plan.

The US Post Office drop box  will be temporarily moved to the east side of the post office building.  Signage will be placed to direct people on where it is located. Click here for the site plan. 

The road should remain open at all time to through traffic, but expect possible delays. The project is expected to be completed by mid-June and is being fully funded by Tax Incremental District (TID) #2. 